Project Acceleration

"We have found their ability to trace and identify system issues and deficiencies extremely helpful. They are a flexible and responsive company who are able to work within the constraints required in occupied research settings."

John Griffith
Senior Project Manager 
Imperial College London

Imperial College and MRC Research Laboratories
Burlington Danes
Inspection and Test and remedial works

We provided inspection and test of new clinical facilities and medical research laboratories. Unfortunately the original installation fell short of the standards required and extensive remedial works resulted.

We also provided scheme design suggestions, planning  and assistance for the rebuild of the fuel pumping and delivery systems for the standby diesel generators.  


We planned and managed extensive black-site switching tests on the occupied buildings, resulting in significant changes to the SCADA system and proving the capabilities of the UPS and diesel generators. We wrote switching scheduals and trained the ICL and FM team in how to switch the building on their main panels and backup systems, as well as on how to monitor and manage the generators and panels via the SCADA system.

We also installed additional main feeders and automatic changeover switchgear, and provided upgrades to the earthing and bonding of Group 1 and Group 2 medical and imaging locations.

Redcentric Data Centres

Redcentric are a managed services company head quartered in Harrogate.  They have Data Centres in Harrogate, Reading, London and Cambridge.  Each Data Centre supports up to 2MVA of load and has a 99.999% or better uptime requirement. 

We provide Redcentric with electrical technical assistance in the design, development and maintenance of the infrastructure of their Data Centres. Our work includes:

-Design and implementation of changes to the various Data Centre electrical distribution systems

-Due diligence before acquisition

-Advice and guidance in the procurement of major plant

-Technical drawing

-Circuit protection and discrimination setting

-Regulatory compliance

-Works quality assurance

Birmingham Airport

Five pumping stations had been left unfinished towards the end of the Birmingham Airport runway extension and road diversion project.  We were called in to help finish the pumping stations, providing inspection, test, remedial works and project acceleration servicesThis included documentation and providing test certification. 

Telford Ice Rink and Soft Play

Following the failure of the original M&E contractor we were engaged to provide 100% third-party inspection and test, prepare a remedial plan and carry out certain remedial works. 

We did this with the building live and operational, allowing business to continue as usual, ensuring the safety of the new electrical installation.

Impact Building Services Ltd
Design Support

Impact are a high quality electrical contractor – for a number of years we have worked alongside them on Data Centre projects. Impact engage us from time to support their designers on calculations for difficult loads such as MRI scanners and medical imaging.

GlaxoSmithKline (GSK)
Clinical Imaging Centre
Faraday cage earth faults

GSK had problems with multiple earth paths on the Faraday cages of 2 MRI rooms. They were getting poor image quality from the scanner installed in one of the rooms.  The other unoccupied MRI room had been half dismantled to try to find fortuitous earth paths.

We injected test currents into the cages and scanner earthing systems and tracked these currents around the cages using their fields. We were able to find fortuitous earth points to within ~20cm non-invasively. Small easily-repaired holes in the stud walls allowed the shorts to be removed and remedied.

Various barrier joints in the services and quench pipes had been badly insulated. Using large custom made current clamps we were easily able to identify and remedy these faulty insulated joints.  

Global EMC
Low Frequency Magnetic Field Measurements
400kV National Grid cables and substation

A low frequency magnetic field survey for Global EMC on a set of National Grid underground 400kV cables and a 400kV substation. These measurements formed the basis for designs of screening a  property development against "electro-smog".